Bid security aur performance guarantee — dono ka maqsad, raqam aur wapsi ka waqt alag hai. Poori tafseel PPRA Rules 2026 ke mutabiq.
Ye guide un ke liye hai jo pehli dafa kisi sarkari tender mein hissa lena chahte hain — chhota thekedar (contractor), supplier, ya koi bhi shakhs jo sarkar ko samaan bechna ya kaam karna chahta hai, lekin use tender ka tareeqa abhi nahi aata.
Is guide ko parhne ke baad aap ye kar sakein ge: (1) bid security aur performance guarantee mein farq samajh sakein ge; (2) khud hisab laga sakein ge ke aap ke tender par kitni raqam deni pare gi; (3) jaan sakein ge ke raqam kab wapas mile gi aur kab zabt (forfeit — hamesha ke liye chale jana) ho sakti hai.
Is guide mein baar baar aane wale alfaz:
Bid security woh raqam ya guarantee hai jo aap bid jama karate waqt dete hain, taa ke agency ko yaqeen ho ke aap apni bid par qaim rahein ge. Performance guarantee woh hai jo sirf kamyab (successful) bidder ko contract milne ke baad deni hoti hai, taa ke agency ko yaqeen ho ke aap kaam poora karein ge.
Wafaqi sarkari khareedari Public Procurement Rules, 2026 ke tehat hoti hai (Gazette SRO 1658(I)/2026, 28 September 2026).
Bid security aik guarantee hoti hai jo bidder apni bid ke saath jama karata hai, taa ke woh bid jama kar ke bila wajah peeche na hate, aur agar use contract mil jaye to dastakhat karne se inkar na kare.
Rule 36 ke mutabiq, agency bidder se bid security mang sakti hai jo estimated value ki:
| Estimated value | Bid security ki zyada se zyada had |
|---|---|
| 250 million Pakistani rupees tak | Estimated value ki 5% se zyada nahi |
| 250 million Pakistani rupees se zyada | Estimated value ki 2% se zyada nahi |
Ye "zyada se zyada" had hai — agency is se kam mang sakti hai. Asal raqam bidding documents mein likhi hoti hai.
Aam tor par bid security pay order (bank ka likha hua hukam ke itni raqam agency ko ada ki jaye), bank guarantee (bank ki tehreeri zamanat ke aap ki zimmedari poori na hone par bank raqam de ga), call deposit (bank mein khas khata jis ki raseed agency ke haq mein hoti hai) ya demand draft (pay order jaisa bank instrument) ki shakal mein hoti hai.
Lekin asal shakal hamesha bidding documents ke mutabiq hoti hai — wahan jo shakal likhi ho, wohi istemal karein.
Aam tor par, jin bidders ko contract nahi milta, un ki bid security evaluation aur award ke baad wapas kar di jati hai. Kamyab bidder ki bid security us waqt tak rakhi jati hai jab tak woh performance guarantee jama na kara de.
Bid security zabt hone ke cases bidding documents mein likhe hote hain — wahi hatmi hain. Lekin Rule 37(4)(c) ke mutabiq, agar agency bid ki validity barhane ki darkhwast kare aur bidder raazi na ho, to woh apni bid baghair bid security zabt hue wapas le sakta hai. Jo bidder raazi ho, usay apni bid security ki validity bhi barhani hoti hai (Rule 37(4)(a)).
Yaad rakhein: Bid security kab zabt ho gi, ye bidding documents mein likha hota hai — bid se pehle woh sharaait parh lein.
Rule 36 ke proviso ke mutabiq, agar agency bid security na mange, to bidder ko bid security declaration jama karani hoti hai — Authority ke muqarar kardah format par, jo standard bidding documents mein hota hai.
Performance guarantee woh guarantee hai jo kamyab bidder contract milne ke baad jama karata hai, taa ke agency ko yaqeen ho ke woh contract ke mutabiq kaam poora kare ga. Rule 2(xxi) ke mutabiq ye bank guarantee, demand draft ya koi aur instrument ho sakti hai, jaisa ke agency tay kare.
Rule 51 ke mutabiq, performance guarantee sirf tab mangi jati hai jab bidding documents mein expressly (saaf tor par) likha ho — warna agency aap se performance guarantee nahi mang sakti.
Rule 51 ke mutabiq, performance guarantee contract amount ki 10% se zyada nahi ho gi. Ye contract amount ki had hai, estimated value ki nahi — aur ye "zyada se zyada" had hai. Asal percentage bidding documents mein likhi hoti hai.
Aam tor par performance guarantee bank guarantee, pay order ya demand draft ki shakal mein hoti hai. Rule 2(xxi) ke mutabiq ye koi aur instrument bhi ho sakti hai, jaisa ke agency tay kare.
Aam tor par performance guarantee kaam mukammal hone par wapas milti hai — jab contract ke mutabiq tamam kaam poora ho jaye aur agency usay qabool kar le.
| Ba'at | Bid Security | Performance Guarantee |
|---|---|---|
| Kab di jati hai? | Bid jama karate waqt | Contract milne ke baad, sirf kamyab bidder |
| Kis se mangi jati hai? | Har bidder se (agar mangi jaye) | Sirf kamyab bidder se |
| Kitni hoti hai? | Estimated value ki zyada se zyada 5% (250 million tak) ya 2% (250 million se zyada) — Rule 36 | Contract amount ki zyada se zyada 10% — Rule 51 |
| Rule | Rule 36 | Rule 51 |
| Kab wapas milti hai? | Aam tor par evaluation aur award ke baad (na-kamyab bidders ko) | Aam tor par kaam mukammal hone par, contract ke mutabiq |
| Kab mangi jati hai? | Jab bidding documents mein likha ho; na mangi jaye to bid security declaration deni hoti hai | Sirf jab bidding documents mein expressly likha ho |
Ab do poori misalein dekhte hain — aik chhote kaam ki, aik bare kaam ki. Raqam "zyada se zyada" had par nikali gayi hai.
Maan lein ke aik sarkari idara aik chhote kaam ke liye tender nikalta hai, jis ki estimated value Rs 50 lakh (Rs 5,000,000) hai.
Misal 1 ka khulasa: Bid security zyada se zyada Rs 250,000 (5%), performance guarantee zyada se zyada Rs 500,000 (10%). Kaam theek ho to dono wapas; ghalti ho to zabt.
Ab aik bara kaam dekhte hain. Maan lein ke aik sarkari idara aik bare mansube ke liye tender nikalta hai, jis ki estimated value Rs 40 crore (Rs 400,000,000) hai.
Misal 2 ka khulasa: Bid security zyada se zyada Rs 8,000,000 (2%), performance guarantee zyada se zyada Rs 40,000,000 (Rs 4 crore) (10%). Kaam theek ho to dono wapas; ghalti ho to zabt.
Dono misalon se aik ahem sabaq: Bid security ka hisab estimated value par hota hai, performance guarantee ka hisab contract amount par hota hai. Ye do alag raqmein hain — inhein mila kar na dekhein.
Bid Security aur Performance Guarantee ke sample templates hamari Downloads page par mojood hain. Ye sirf sample hain, official PPRA forms nahi.
Nahi. Rule 36 ke mutabiq agency bid security "mang sakti hai" — ye lazmi nahi. Agar na mangi jaye to bid security declaration jama karani hoti hai.
Bidding documents mein jo forfeiture ki sharaait likhi hon, wohi hatmi hain. Lekin Rule 37(4)(c) ke mutabiq, validity barhane se inkar par aap bid baghair forfeiture wapas le sakte hain.
Contract amount ka 10% zyada se zyada had hai. Misal: Rs 25,000,000 ke contract par zyada se zyada Rs 2,500,000. Asal percentage bidding documents mein likha hota hai.